Projects Journal
Page 7

This page updated: Thursday, March 27, 2008


Projects Journal Index:
Page 1
(Bedside Table; Kitchen Cabinets)
Page 2 (Trivet; Writing Desk; Trad. End Table; Lamp)
Page 3
(A&C Coffee Table; TV Cabinet; Walnut Coffee Table; A&C End Table)
Page 4 (Walnut Hall Table; Granite Top Mission Table; Mission Hall Table)
Page 5 (708 Style Writing Table) (Mission Trestle Table)
Page 6 (Arts and Crafts Bench)
Page 7 (New Construction 2005-Kitchen)
Page 8 (Tool Drawers; Stacked Tansu)
Page 9 (Plan Rack; Door Restoration; Spice Rack; A&C House# Frame)
Page 10 (Craftsman Chair Reproduction)
Page 11 (A&C Kitchen Dining Set)
Page 12 Cherry/Walnut Hope Chest)
Page 13 (Mission Sideboard)
Page 14 (Kitchen Drawers; Calendar Frames)
Page 15 (Corner Cabinet)
Page 16 (2008 Kitchen Project/Trash Pullout)

 

Kitchen In New Residential Construction- 2005

 

A good deal of planning and drawing that will not be evident on this page goes into a new kitchen project. I will be glad to e-mail a zip file that contains actual evidence of this fact in the way of drawings and cutlists to anyone who is interested ... just ask for it in rec.woodworking, making sure beforehand that you can actually receive attachments by e-mail.

 Long story short, the cabinets you see here were all designed by me using QuickCAD and CutList Plus for the parts, materials, and cut lists, then built in my shop starting a few months before this house was started, all necessary steps when you work alone. The cabinets were then placed in storage awaiting the steps that you see on this page. Everyone has a favorite methods of building cabinets and I do it the old fashioned way, using traditional face frame construction, top grade 3/4" oak plywood for the carcasses, with raised panel doors and solid maple drawers. Although much can be gleaned from the drawings in the above mentioned file (two examples above), I will be glad to answer any questions in that forum.



Day 1 - April 14, 2005 (placement and checkout of space)

   

Cabinets moved to site and installation begins. Wall cabinets in these pictures are just roughed in and resting on leveled* 2 x 3's screwed to studs. They have yet to be shimmed, leveled, and screwed firmly into the blocking which I had the framing crew install during that stage of the construction, The base cabinets and two island cabinets are just resting in their approximate location for a level check, and to line up the wall cabinets above for the rough-in.

 At this stage I generally leave them "easy to adjust" until the base cabinets look like they are going to fit the wall space (as with any installation in new construction, and despite meticulous planning, until the floors and sheetrock are in you are working in a basically unknown space, with the exact dimensions up for grabs, and you never really know what surprises are in store). Also for that reason, and particularly in an angled configuration like the above, I generally leave the two cabinets on either side of the sink base until last so that I can dimension them precisely (I dislike "spacers" in a custom kitchen, as the idea of "custom" to me is insuring that all space is functional space). Most importantly, this also insures that the sink insert will be flush with the back wall and that expensive granite will fit perfectly.

Bottom line at this stage is that there are still two small, sliding drawer, 'spice rack' cabinets that are yet to be built. I will knock them out in the morning. All I really need to do is to make their face frames and use those as temporary 'spacers' between the sink base and the adjacent cabinets, which would allow me to go ahead and install the adjacent line of base cabinets ... another advantage to making your face frames first ... but in this instance these two base cabinets will be small and can be put together in couple of hours because the shop is already set up for this type work.

All in all, and from what I've seen today, I am comfortable that this kitchen should go in nicely.

* Someone e-mailed and wanted to know about "level" and how and where do you start to establish this all important line:

I scribe a "reference line" around the perimeter walls, somewhere between the top of the base cabinet and the bottom of the wall cabinets. I generally use a mark at 35 1/2" above the floor (1" above the top of the base cabinets, sans substrate and countertops) and then carry this reference line around the walls, using a level (in the old days), a water level hose (in the days when you were confident about passing the Mensa IQ test), or nowadays (the lazy ones), a laser level.

Once this line is established, you can determine the high spots in the floor (places where the distance from your "reference line" to the floor is less than 35 1/2" (I think that may have been on that IQ test)).

 The highest spot is the spot that I use to establish the exact height of the lower line of the wall cabinets. This reference line also lets you determine where you will need shims, and shows up any possible trouble spots in leveling your line of cabinets ... a must for granite or natural stone countertops. 

 

Day 2 and 2 1/2  - April 15 & 16, 2005 (Leveling, shimming and installation)

 

The two narrow cabinets on either side of the sink base, which will hold pullout spice/cookie sheet racks (and which in most "factory built box" installations would be useless 'spacers'), were built in the shop Friday morning, transported to the site, and installed on either side of the sink base, making one solid unit.

The entire line of wall and base cabinets on the East wall have been shimmed and fastened into place with #8 3" wood screws through the bottom and top hanger plates into the previously installed 2" x 6" backing behind the sheetrock; and with 1/4" x 3" lag screws, with washers, through the top hanger plate.

These lag screws are considered overkill by many, but they guarantee I won't be waking up at 3 AM ten years from now worrying about whether future occupants might attempt to store their 800 pounds of priceless Egyptian artifacts in my kitchen cabinets.

During this entire operation the Face Frames of adjoining cabinets are flushed and fastened together with #8 2 1/2" lubricated wood screws, and the leveling 2 x 3's removed.

The last two pictures show the hidden "toe kick" drawers in the two base cabinets which flank the stove. Depending upon your lifestyle, these can hold anything from cookie sheets, to your stash, your valuables, or your weaponry of choice.

Actually, the ones pictured are just "dummy" drawers intended to perform the function of insuring that the slides work after the necessary shimming and leveling (examples of said shimming which are visible above along the walls and between units). The real drawers will be built during the next couple of weeks and replace the dummies.

Not to mention that it is a lot easier on the knees of old "One-Sock-Hung-Low" (pictured above, proudly testing the solidness of the installation) to have those cabinet-side drawer slide components installed so he doesn't have to try to resume an upright position after attempting to install them at floor level.

The older you get, the more you have to take such minor details into consideration.

 

Day 3 and 4  - April 18 & 19, 2005 (finish installation and start trim-out)

 

At the end of the day on Tuesday, all base cabinets have been leveled, shimmed and installed by screwing to the blocking previously added behind the sheetrock, the plywood substrate added for the countertops, visible edges trimmed out (seen in the first three pictures above),  and crown molding added to top of the wall cabinet run (the bottom oak trim for the wall cabinets is back ordered and will have to be installed later). All the electrical and plumbing rough-in has been coordinated with both contractors, and the countertops and backsplashes can now be installed without further ado. Sometime in the next few days, and as the opportunity arises, I will rip some 3/8" oak plywood for a more or less seamless run of kick plate.

At this point it is time to get out of the way, let the granite and tile installers have a go, and it's back to the shop to complete the drawers, doors and add-ins. The kick plates and any additional trim can be added later as long as it is done before the paint contractor is scheduled to start.

The granite and tile crew will be in the house about at week to ten days, all things going smoothly.

 

Day 5  - April 23, 2005 (Granite countertop installation)

 

 

The  granite on the kitchen countertops were done first and then covered with contractor's paper for protection while the backsplashes go in. The backsplashes will take a bit longer, as they are individual stone tiles set in a diamond pattern.

There are only two seams in the entire granite countertop surface - about a foot to the right of the sink just before the wall angles back toward the stove space; and where the base cabinets go from 24" depth to 12" under the far window in the last picture above. The granite on the island is one piece and is cut beautifully to follow the fair curve I laid out and cut into the substrate. These guys are good, do the kind of work that complements my cabinets, and their attention to detail is on a par with the quality built into the cabinets themselves!

I also like the "waterfall" edge on the granite, particularly along that curve in the island. The "bullnose" edge is most often seen on builder installations hereabouts  ... the waterfall edge is much classier, IMO.

The trim for the bottom of the cabinets has arrived, but I will wait until the backsplashes are in to install it so that it can be butted up against that surface, giving a more finished appearance overall ... it's these details, even coming down to the order of doing things, that give the project that little extra 'something'. 

 

May 4,  2005 (Backsplash installation)

The  backsplash installation has been completed by the tile crew, in the kitchen, as well as throughout the house. The bottom trim will be applied to the cabinet boxes and at that point they will be ready for final sanding and staining. While the granite and tile installation progressed, the drawers, drawer fronts, and doors were being finished. All should be ready for the paint contractor in the next few days. After his crew does their work, we will cover and tape the entire assembly for the time that it takes to get the surrounding walls in the house spray painted..

On that note, I have just about decided to forego the usual drawer slides from Blum or Accuride and go with Hittich QuadroV6 under mount, full extension drawer slides. I picked up a sample slide and built a prototype drawer as a test. Although these drawer slides cost more and require a few more steps when building the drawers, they are sturdy, very quiet, and have a very nice, expensive feel on opening and closing, drawing further attention to the quality that is built into this job.

 

May 20, 2005 (cabinets uncovered and doors hung)

     

After all the trim was applied and the stain and finishing steps were completed, the cabinets were taped and covered for the past two weeks to protect them while the kitchen and surrounding walls were being spray painted.

I just uncovered them today and mounted the cabinet doors, the drawer slides, and set the maple drawers temporarily in place to make sure there were no problems since I haven't used this particular type of drawer slide before and wanted to make sure that the dimensions were absolutely dead on. The drawers will now be taken back to the shop and finished out with the under mount hardware catches that hold them on the Hittich full extension slides, the drawers will then be sprayed with an amber shellac finish before being re-mounted. After that I will install the spice rack drawers and apply all the drawer fronts.

 

June 2005 - Wrapped up

For all practical purposes this kitchen is finished and ready for use: 

20/20 Hindsight Department:  Except for taking one of the hardwood floor finishing crew's kids as a hostage on the next one ... at least until they successfully do their thing without creaming one of my precious cabinet doors with a floor sander (most folks would have "repaired and refinished". NOT in any of my kitchens, thank you, It was replaced with a new one) ... there is not much to re-think or second guess on this one.

The installation went well, with few hitches, and those few that did arise were minor and easily solved, a circumstance which is not always the case. That's the nice thing about building the house where you're putting your cabinets ... you can take those extra steps that make the process go smoothly before you ever build a cabinet. That said, the electricians, despite my best efforts, and their presence for just that eventuality before the cabinets went in, did manage to lose a hot circuit BEHIND the kitchen cabinets and were in a tizzy until I pulled up the digital photos of the electrical and plumbing rough-in that I always take before insulation and sheetrock go up (it was behind the dishwasher cabinet and the photos allowed us to pinpoint it to the 1/4" and retrieve it as if the cabinets weren't there ... it's those kind of things that make you a hero to your pocket book, if to no one else).

I very much like the under-mount Hittich drawer slides and will most definitely use them again, but you do need to make your drawers to accommodate their peculiarities. I am also glad I took the time to make the toe kick drawers on either side of the stove ... a nice touch ... but just remember to repeatedly remind, in at least two languages, the floor finishing crew (those guys again!) to NOT nail down the shoe molding in front of them!

All in all, due mainly to the extensive and meticulous planning that went into it <ahem>, this project completed nicely, uneventfully and with a great deal of pride. Amazing how that works, isn't it?!

 


Page 1 (Bedside Table; Kitchen Cabinets)
Page 2 (Trivet; Writing Desk; Trad. End Table; Lamp)
Page 3
(A&C Coffee Table; TV Cabinet; Walnut Coffee Table; A&C End Table)
Page 4 (Walnut Hall Table; Granite Top Mission Table; Mission Hall Table)
Page 5
(708 Style Writing Table) (Mission Trestle Table)
Page 6 (Arts and Crafts Bench)
Page 7 (New Construction-2005 Kitchen)
Page 8 (Tool Drawers; Stacked Tansu)
Page 9 (Plan Rack; Door Restoration; Spice Rack; A&C House# Frame)
Page 10 (Craftsman Chair Reproduction)
Page 11 (A&C Kitchen Dining Set)
Page 12 (Cherry/Walnut Hope Chest)
Page 13 (Mission Sideboard)
Page 14 (Kitchen Drawers; Calendar Frames)
Page 15 (Corner Cabinet)
Page 16 (2008 Kitchen Project/Trash Pullout)

Back to home page